Hòn Khoai is officially a "dual-use general port" (built for both commercial cargo and national defense use) situated on the Hòn Khoai island cluster off Cà Mau province, at Vietnam's southernmost tip.
Rendering of the planned port layout: container yards, breakwater, and fuel/LNG terminal. Source: Thanh Niên
"Cảng Hòn Khoai được xây dựng tại xã Đất Mũi, cách đất liền 17 km, gồm bến tàu dài 1.000 m, công suất 20 triệu tấn hàng hóa mỗi năm."
"Hòn Khoai Port is being built in Đất Mũi commune, 17 km from the mainland, with a 1,000m wharf and a capacity of 20 million tonnes of cargo per year."
VnExpress, "Hòn Khoai - đảo tiền tiêu chiến lược vùng biển Tây Nam" · vnexpress.net
"Công trình còn có đê chắn sóng, kè bảo vệ, hạ tầng kỹ thuật phục vụ cả hoạt động dân sự và quân sự."
"The project also includes breakwaters, protective revetments, and technical infrastructure serving both civilian and military activity."
Data discrepancy: flagged for transparency
One government-linked report gives the shipping channel dredging figures as 5.6 km long, 250 m wide, with a 600 m turning basin, while a separate industry-news outlet reports 5,000 m long, 230 m wide, with an 800 m turning basin, citing the same groundbreaking event. Both are quoted below; we are not able to resolve which is more current from the sources available to us.
"Nạo vét luồng tàu (dài 5,6km, bề rộng 250 m), khu quay trở tàu (đường kính 600m)..."
Báo Xây Dựng, "Cà Mau: Sẽ có cảng tổng hợp lớn nhất Đồng bằng sông Cửu Long" · baoxaydung.vn
"Dự án này cũng gồm nạo vét mở mới 1 luồng tàu dài khoảng 5.000m, rộng 230 m và vũng quay tàu đường kính 800 m."
Báo Đấu Thầu, "Khởi công loạt dự án hạ tầng chiến lược tại Cà Mau" · baodauthau.vn
Ownership and Investor
The project is unambiguously state/military-owned: every source we found agrees on this point, with no conflicting reports.
"Cảng tổng hợp lưỡng dụng Hòn Khoai, do Quân chủng Hải quân làm chủ đầu tư."
"The Hòn Khoai dual-use general port, invested by the Vietnam People's Navy."
Báo Hải quân Việt Nam, "Lễ khởi công Cảng tổng hợp lưỡng dụng Hòn Khoai" · baohaiquanvietnam.vn
"Dự án Cảng Hòn Khoai là dự án trọng điểm quốc gia thuộc Bộ Quốc phòng."
"The Hòn Khoai Port Project is a nationally strategic project under the purview of the Ministry of National Defence."
Tan Cang Offshore Services JSC, 2026 Annual General Meeting Minutes (official company disclosure, filed with the State Securities Commission and Hanoi Stock Exchange, 21 May 2026)
Design Capacity and Scale
"...quy mô xây dựng 1 bến tàu dài 1.000 m, công suất 20 triệu tấn/năm. Cảng Hòn Khoai có thể tiếp nhận tàu đến 250.000 DWT."
"...built to a scale of one 1,000m berth, with a capacity of 20 million tonnes/year. Hòn Khoai Port can receive vessels of up to 250,000 DWT."
"Ở giai đoạn hoàn thiện, cảng sẽ mở rộng lên 686 ha, có thêm hai cầu cảng tổng hợp dài 1.000 m đón tàu container 250.000 DWT và hai cầu cảng hàng lỏng, khí, tiếp nhận tàu 150.000 DWT."
"At the completion stage, the port will expand to 686 ha, adding two 1,000m general-cargo berths for 250,000 DWT container vessels, and two liquid/gas berths receiving vessels up to 150,000 DWT."
The full construction breakdown from the groundbreaking-day report:
"Xây dựng công trình khu cảng thương mại gồm: Bến cập tàu dài 1.000m; hệ thống 5 cầu dẫn; hệ thống kè bảo vệ bờ tổng chiều dài khoảng 1.600m; kè bảo vệ bờ kết hợp đê chắn sóng dài khoảng 560m; đê chắn sóng tổng chiều dài 3.920m."
"Construction of the commercial port zone includes: a 1,000m berth; a system of 5 approach bridges; shoreline revetment totaling about 1,600m; combined revetment/breakwater of about 560m; and breakwater totaling 3,920m."
"Dự án có tổng diện tích 590,5ha. Cụ thể, tôn tạo mặt bằng 82ha để xây dựng các hạng mục công trình gồm: Khu cảng khai thác thương mại có diện tích 59,1ha và khu hạ tầng kỹ thuật dùng chung có diện tích 14,3ha và các khu vực khác 8,6ha."
"The project has a total area of 590.5 ha. Specifically, 82 ha of land will be reclaimed, comprising a 59.1 ha commercial port zone, a 14.3 ha shared technical-infrastructure zone, and 8.6 ha of other areas."
The port sits within a larger, jointly-launched infrastructure package. The connecting sea-crossing bridge and the regional expressway are separate, much larger-budget projects announced the same day:
"Dự án đường giao thông ra đảo Hòn Khoai (mức đầu tư khoảng 25.715 tỷ đồng) có chiều dài cầu vượt biển khoảng 18,22 km."
"The road project to Hòn Khoai island (investment of approximately VND 25,715 billion) includes a sea-crossing bridge about 18.22 km long."
"Điểm đầu cầu phía đất liền nối với cao tốc Cà Mau - Đất Mũi, dài hơn 80km... vốn gần 59.000 tỷ đồng, cũng dự kiến hoàn thành năm 2028."
"The mainland end connects to the Cà Mau–Đất Mũi expressway, over 80km long... with investment of nearly VND 59,000 billion, also targeted for completion in 2028."
VietnamNet, "Toàn cảnh dự án cầu vượt biển nơi cực Nam Tổ quốc dài hơn 18 km" · vietnamnet.vn
Our reading, not a stated fact
Taken together, these figures suggest the "Hòn Khoai" development is best understood as a roughly VND 100,000-billion-scale regional infrastructure push (port + bridge + expressway combined), not a single VND 15,000 billion project in isolation. No source we found states a combined total explicitly, so this sum is our own addition of the three disclosed figures, not a reported figure.
Progress Timeline
"Sáng 19/8, tại Cà Mau, Bộ Quốc phòng phối hợp cùng UBND tỉnh Cà Mau tổ chức Lễ khởi công các dự án trọng điểm: tuyến cao tốc Cà Mau-Đất Mũi, tuyến giao thông kết nối từ Mũi Cà Mau ra đảo Hòn Khoai và Cảng tổng hợp lưỡng dụng Hòn Khoai."
"On the morning of 19 August, in Cà Mau, the Ministry of National Defence and the Cà Mau Provincial People's Committee held a groundbreaking ceremony for key projects: the Cà Mau–Đất Mũi expressway, the road connecting Mũi Cà Mau to Hòn Khoai island, and the Hòn Khoai dual-use general port."
"Đại tướng Phan Văn Giang, Ủy viên Bộ Chính trị, Phó bí thư Quân ủy Trung ương, Bộ trưởng Bộ Quốc phòng dự và phát biểu chỉ đạo tại lễ khởi công."
"General Phan Văn Giang, Politburo member, Deputy Secretary of the Central Military Commission, and Minister of National Defence, attended and gave a directional speech at the groundbreaking ceremony."
As of the most recent progress reporting we could locate (June 2026), the connecting bridge (and by extension the wider island development) was still under active, if early-stage, construction:
The sea-crossing route and port site under construction, shortly after the 19 August 2025 groundbreaking. Photo: G.B. / Thanh Niên
"...các hạng mục phụ trợ phục vụ hậu cần và thi công biển cũng đang được đẩy nhanh để đảm bảo mục tiêu hoàn thành vào cuối năm 2028. Dự án bao gồm tuyến chính dài 17,4km và tuyến nhánh dài 0,85km, kết nối trực tiếp từ khu vực Đất Mũi đến cảng Hòn Khoai."
"...supporting logistics and marine construction works are also being accelerated to meet the target completion by the end of 2028. The project comprises a 17.4km main route and a 0.85km branch route, connecting directly from the Đất Mũi area to Hòn Khoai port."
Báo Lâm Đồng, "Cầu vượt biển Hòn Khoai tại Cà Mau: Tiến độ và quy mô công trình kỷ lục" (June 2026) · baolamdong.vn
Strategic Importance
"Với độ sâu mực nước tự nhiên lớn, vùng biển Hòn Khoai có thể tiếp nhận tàu trọng tải trên 250.000 tấn mà không cần nạo vét nhiều, hiếm có ở Việt Nam."
"With significant natural water depth, the waters around Hòn Khoai can receive vessels over 250,000 tonnes without extensive dredging, a rare characteristic in Vietnam."
Công Thương, "Cảng Hòn Khoai: Điểm trung chuyển trọng yếu của đồng bằng sông Cửu Long" · congthuong.vn
"Đặc biệt, cảng có hệ thống đê chắn sóng, kè bảo vệ, khu vực cập tàu quân sự, doanh trại và hạ tầng phụ trợ, đảm bảo vai trò 'hai trong một': phục vụ phát triển kinh tế và nhiệm vụ quốc phòng."
"Notably, the port has breakwaters, protective revetments, a military berthing area, barracks, and supporting infrastructure, ensuring a 'two-in-one' role: serving economic development and national defense duties."
Thanh Niên, "Hòn Khoai - 'cánh cửa ngoài khơi' trên biển Tây Nam" · thanhnien.vn
"Cảng Hòn Khoai được kỳ vọng trở thành cửa ngõ giao thương quan trọng của Cà Mau nói riêng và khu vực Tây Nam Bộ nói chung."
"Hòn Khoai Port is expected to become an important trade gateway for Cà Mau specifically and the wider Southwestern region generally."
CafeF, "Tấp nập thi công cầu đường vượt biển dài nhất Việt Nam" · cafef.vn
"Không ít chuyên gia nhìn nhận, việc triển khai đồng bộ các dự án hạ tầng trên đảo Hòn Khoai chính là sự cụ thể hóa quan điểm 'phát triển kinh tế gắn liền với bảo vệ Tổ quốc từ sớm, từ xa'."
"A number of experts view the synchronized rollout of infrastructure projects on Hòn Khoai island as the concrete realization of the principle of 'economic development linked with defending the homeland early, from a distance.'"
Tan Cang Offshore Services JSC (ticker: TOS, legal name TCO) is named in press coverage of the groundbreaking as one of three construction contractors on the project, not the owner and not the sole contractor.
"Các nhà thầu thi công gồm Công ty TNHH Đầu tư xây dựng DACINCO; Công ty Cổ phần xây lắp Thành An 96; Công ty Cổ phần dịch vụ biển Tân Cảng (TCO). Đơn vị giám sát là Công ty Cổ phần Tư vấn xây dựng Công trình Hàng hải và Viện kỹ thuật Công trình đặc biệt."
"The construction contractors are DACINCO Investment Construction Co., Ltd.; Thành An 96 Construction JSC; and Tan Cang Offshore Services JSC (TCO). The supervision units are Maritime Construction Consulting JSC and the Institute of Special Engineering."
Báo Xây Dựng · baoxaydung.vn (also independently corroborated by SGGP, "Sẵn sàng khởi công Cảng tổng hợp lưỡng dụng Hòn Khoai")
TOS's own board confirmed this role directly to shareholders: this is the single most authoritative statement available, since it comes from the company itself in an official regulatory filing rather than press reporting:
"Đối với vai trò của TCO trong dự án Cảng Hòn Khoai: Dự án Cảng Hòn Khoai là dự án trọng điểm quốc gia thuộc Bộ Quốc phòng. Hiện nay, Bình đoàn 20 – Công ty TNHH MTV Tổng công ty Tân Cảng Sài Gòn và TCO tham gia dự án với vai trò thực hiện nhiệm vụ theo phân công/chỉ đạo."
"Regarding TCO's role in the Hòn Khoai Port Project: the Hòn Khoai Port Project is a nationally strategic project under the Ministry of National Defence. At present, Group 20 – Saigon Newport Corporation One Member Limited Liability Company and TCO are participating in the project in the capacity of executing assigned tasks pursuant to directives and organizational assignments."
Tan Cang Offshore Services JSC, Minutes of the 2026 Annual General Meeting of Shareholders, Section 2.5 (filed 21 May 2026 with the State Securities Commission and Hanoi Stock Exchange)
Our reading, not a stated factThe company's own wording is deliberately vague: "executing assigned tasks pursuant to directives" doesn't specify which construction package, phase, or dollar value TOS is responsible for. Press coverage of the groundbreaking names DACINCO first, and one outlet's summary line singles it out alone as "the construction contractor." Based on that ordering, our inference is that TOS most likely holds a secondary or delegated role rather than the primary contract, though this is our reading of how the press described it, not something any source states outright.
What TOS's Own Financial Statements Show
Rather than rely only on commentary, we pulled figures directly from TOS's audited Q2 2026 consolidated financial statements (period ended 30 June 2026, filed with comparatives as at 1 January 2026). Two line items are relevant.
Construction-in-progress (Note V.12 to the consolidated balance sheet):
Item (VND)
30 Jun 2026
1 Jan 2026
Change
Acquisition of fixed assets
426,786,909,337
551,392,626,934
−124,605,717,597
Construction-in-progress
305,092,155,708
18,764,413,956
+286,327,741,752
Major repair of fixed assets
2,225,666,304
2,533,154,550
−307,488,246
Total
734,104,731,349
572,690,195,440
+161,414,535,909 (+28.2%)
Source: Tan Cang Offshore Services JSC, Consolidated Financial Statements Quarter II 2026, Note V.12 "Construction-in-progress." The overall +28.2% growth in total construction-in-progress is driven almost entirely by the "Construction-in-progress" sub-line, which grew roughly 16.3-fold, partly offset by a decline in "Acquisition of fixed assets."
Advances from customers, Vietnam People's Navy specifically (Note V.14 to the consolidated balance sheet):
Item (VND)
30 Jun 2026
1 Jan 2026
Change
Short-term advances: Vietnam People's Navy
950,046,868,573
614,795,575,343
+335,251,293,230 (+54.5%)
Long-term advances: Vietnam People's Navy
414,009,317,300
434,767,672,700
−20,758,355,400 (−4.8%)
Combined Navy advances
1,364,056,185,873
1,049,563,248,043
+314,492,937,830 (+30.0%)
Source: Tan Cang Offshore Services JSC, Consolidated Financial Statements Quarter II 2026, Note V.14 "Advances from customers." The Vietnam People's Navy is TOS's single largest source of customer advances in both periods shown.
Important limitation
Neither of these two notes names "Hòn Khoai" specifically. The financial statements report only generic categories ("Construction-in-progress") and a customer name ("Vietnam People's Navy"), with no project-level breakdown disclosed, so the direct revenue contribution from Hòn Khoai specifically cannot be sized from public information. TOS has separately stated in its own AGM Q&A that it cannot disclose further contract-level detail due to confidentiality and partner requirements:
"Trong thời gian tới, Công ty tiếp tục tích cực tham gia đấu thầu nhiều dự án đầu khí trong và ngoài nước. Tuy nhiên, do yêu cầu bảo mật thông tin kinh doanh và quy định của đối tác, Công ty chưa thể công bố chi tiết tại Đại hội."
"Going forward, the Company will continue to actively participate in tendering for oil and gas projects both domestically and internationally. However, due to business confidentiality requirements and partner-imposed regulations, the Company is not in a position to disclose further details at this General Meeting."
TOS 2026 AGM Minutes, Section 2.3 (this specific quote refers to oil & gas tenders, cited here to show the company's general pattern of non-disclosure on contract-level detail, not a direct statement about Hòn Khoai)
Our reading, not a stated fact
We think it's reasonable to read these two data points (rising construction-in-progress and a rising Navy advance balance in the same period, from a company that has confirmed participation in a Navy-owned port project) as the strongest available, though still circumstantial, evidence that Hòn Khoai, and possibly related Navy infrastructure like the connecting bridge, is a contributor to this growth. TOS's Navy relationship could include other contracts we aren't aware of, and the company hasn't disclosed a project-level split, so treat this as a hypothesis to verify, not a confirmed link.
Broader Financial Context (Not Project-Specific)
Separately, analyst commentary (not TOS's own disclosure) places Hòn Khoai within a wider list of Navy/defense-linked projects TOS is said to benefit from:
"Nhờ nằm trong hệ sinh thái của Quân chủng Hải Quân (Bộ quốc phòng) nên TOS được tham gia vào nhiều dự án hạ tầng và quốc phòng quy mô lớn như Cảng Hòn Khoai (15.000 tỷ), cầu vượt biển kết nối với đảo Hòn Khoai (25.000 tỷ), Bến số 7&8 tại cảng nước sâu Lạch Huyện (12.792 tỷ)."
"Because it sits within the Vietnam People's Navy (Ministry of National Defence) ecosystem, TOS is able to participate in numerous large-scale infrastructure and defense projects such as Hòn Khoai Port (15,000 billion), the sea-crossing bridge connecting to Hòn Khoai island (25,000 billion), and Berths 7&8 at Lạch Huyện deep-water port (12,792 billion)."
Alias.vn, "TOS - Khối lượng công việc tăng cao kỷ lục" (equity research commentary, not TOS's own disclosure) · alias.vn
Important limitation
This is third-party analyst commentary, not a company or government filing. We have not independently verified TOS's specific contract value or scope on Hòn Khoai from a primary source, and none exists in what we could find publicly. Treat the VND figures attached to each named project in this quote as that analyst's characterization, not confirmed contract values disclosed by TOS. TOS's participation also appears to be one input among several Navy/defense-linked infrastructure projects, so Hòn Khoai alone may not be separable from TOS's broader "defense ecosystem" revenue stream.
The same commentary source also cites an end-Q3/2025 figure for TOS's customer advances from the Vietnam People's Navy: VND 1,916 billion, up more than 500 billion since the start of that year. This predates the Q2/2026 figures above (combined Navy advances of VND 1,364 billion as at 30 June 2026) and, without TOS's intervening quarterly filings, the two aren't directly comparable. alias.vn
Growth and Importance to TOS: Our Assessment
Our analysis: explicitly our own view, not sourced fact
Hòn Khoai is plausibly a meaningful and growing contributor to TOS's construction-in-progress and customer-advance balances, but the public record does not allow us (or, as far as we can tell, any outside analyst) to state a confirmed revenue or profit figure attributable to this specific project. Anyone using this relationship for investment purposes should treat it as a thesis requiring further verification (e.g., through direct company enquiry or subsequent quarterly disclosures), not a settled fact.
⚓
Cảng Hòn Khoai: Tổng quan nhanh
Chủ đầu tư
Quân chủng Hải quân (Bộ Quốc phòng)
Vị trí
Cụm đảo Hòn Khoai, Đất Mũi, tỉnh Cà Mau
Công suất thiết kế
20 triệu tấn/năm (giai đoạn đầu)
Cỡ tàu tối đa
Đến 250.000 DWT
Tổng diện tích
590,5 ha
Vốn đầu tư ước tính
~15.000 tỷ đồng (riêng phần cảng)
Khởi công
19/8/2025, tại Cà Mau
Nhà thầu
DACINCO, Thành An 96, Công ty CP Dịch vụ biển Tân Cảng (TOS/TCO)
Hòn Khoai chính thức là một "cảng tổng hợp lưỡng dụng" (được xây dựng phục vụ cả hàng hóa thương mại lẫn mục đích quốc phòng) nằm trên cụm đảo Hòn Khoai ngoài khơi tỉnh Cà Mau, ở điểm cực Nam của Việt Nam.
Phối cảnh quy hoạch cảng: bãi container, đê chắn sóng và khu bồn chứa nhiên liệu/LNG. Nguồn: Thanh Niên
"Cảng Hòn Khoai được xây dựng tại xã Đất Mũi, cách đất liền 17 km, gồm bến tàu dài 1.000 m, công suất 20 triệu tấn hàng hóa mỗi năm."
VnExpress, "Hòn Khoai - đảo tiền tiêu chiến lược vùng biển Tây Nam" · vnexpress.net
"Công trình còn có đê chắn sóng, kè bảo vệ, hạ tầng kỹ thuật phục vụ cả hoạt động dân sự và quân sự."
Chênh lệch dữ liệu: nêu rõ để minh bạch
Một báo có liên kết với cơ quan nhà nước đưa ra thông số nạo vét luồng tàu là dài 5,6 km, rộng 250 m, với vũng quay tàu đường kính 600 m, trong khi một tờ báo ngành khác lại đưa ra con số 5.000 m chiều dài, 230 m chiều rộng, vũng quay tàu 800 m, cùng dẫn về sự kiện khởi công. Cả hai được trích dẫn bên dưới; tôi không có đủ căn cứ để xác định số liệu nào chính xác/cập nhật hơn từ các nguồn hiện có.
"Nạo vét luồng tàu (dài 5,6km, bề rộng 250 m), khu quay trở tàu (đường kính 600m)..."
Báo Xây Dựng, "Cà Mau: Sẽ có cảng tổng hợp lớn nhất Đồng bằng sông Cửu Long" · baoxaydung.vn
"Dự án này cũng gồm nạo vét mở mới 1 luồng tàu dài khoảng 5.000m, rộng 230 m và vũng quay tàu đường kính 800 m."
Báo Đấu Thầu, "Khởi công loạt dự án hạ tầng chiến lược tại Cà Mau" · baodauthau.vn
Chủ đầu tư và Sở hữu
Dự án rõ ràng thuộc sở hữu nhà nước/quân đội: mọi nguồn tôi tìm được đều thống nhất ở điểm này, không có báo cáo trái chiều nào.
"Cảng tổng hợp lưỡng dụng Hòn Khoai, do Quân chủng Hải quân làm chủ đầu tư."
Báo Hải quân Việt Nam, "Lễ khởi công Cảng tổng hợp lưỡng dụng Hòn Khoai" · baohaiquanvietnam.vn
"Dự án Cảng Hòn Khoai là dự án trọng điểm quốc gia thuộc Bộ Quốc phòng."
Công ty CP Dịch vụ biển Tân Cảng, Biên bản họp Đại hội đồng cổ đông thường niên 2026 (tài liệu công bố chính thức, nộp Ủy ban Chứng khoán Nhà nước và Sở GDCK Hà Nội, ngày 21/5/2026)
Công suất thiết kế và Quy mô
"...quy mô xây dựng 1 bến tàu dài 1.000 m, công suất 20 triệu tấn/năm. Cảng Hòn Khoai có thể tiếp nhận tàu đến 250.000 DWT."
"Ở giai đoạn hoàn thiện, cảng sẽ mở rộng lên 686 ha, có thêm hai cầu cảng tổng hợp dài 1.000 m đón tàu container 250.000 DWT và hai cầu cảng hàng lỏng, khí, tiếp nhận tàu 150.000 DWT."
Toàn bộ hạng mục xây dựng theo báo cáo ngày khởi công:
"Xây dựng công trình khu cảng thương mại gồm: Bến cập tàu dài 1.000m; hệ thống 5 cầu dẫn; hệ thống kè bảo vệ bờ tổng chiều dài khoảng 1.600m; kè bảo vệ bờ kết hợp đê chắn sóng dài khoảng 560m; đê chắn sóng tổng chiều dài 3.920m."
"Dự án có tổng diện tích 590,5ha. Cụ thể, tôn tạo mặt bằng 82ha để xây dựng các hạng mục công trình gồm: Khu cảng khai thác thương mại có diện tích 59,1ha và khu hạ tầng kỹ thuật dùng chung có diện tích 14,3ha và các khu vực khác 8,6ha."
Cảng nằm trong một gói hạ tầng khu vực lớn hơn được khởi công cùng ngày. Cầu vượt biển kết nối và tuyến cao tốc khu vực là các dự án riêng biệt, có ngân sách lớn hơn nhiều:
"Dự án đường giao thông ra đảo Hòn Khoai (mức đầu tư khoảng 25.715 tỷ đồng) có chiều dài cầu vượt biển khoảng 18,22 km."
"Điểm đầu cầu phía đất liền nối với cao tốc Cà Mau - Đất Mũi, dài hơn 80km... vốn gần 59.000 tỷ đồng, cũng dự kiến hoàn thành năm 2028."
VietnamNet, "Toàn cảnh dự án cầu vượt biển nơi cực Nam Tổ quốc dài hơn 18 km" · vietnamnet.vn
Cách hiểu của tôi, không phải sự thật đã nêu
Gộp chung các con số này, tôi cho rằng dự án "Hòn Khoai" nên được hiểu là một gói hạ tầng khu vực có quy mô khoảng 100.000 tỷ đồng (cảng + cầu + cao tốc cộng lại), chứ không phải một dự án đơn lẻ trị giá 15.000 tỷ đồng. Không có nguồn nào tôi tìm được nêu rõ con số tổng cộng này: đây là phép cộng ba con số đã công bố do tôi tự thực hiện, không phải một số liệu đã được báo cáo.
Tiến độ
"Sáng 19/8, tại Cà Mau, Bộ Quốc phòng phối hợp cùng UBND tỉnh Cà Mau tổ chức Lễ khởi công các dự án trọng điểm: tuyến cao tốc Cà Mau-Đất Mũi, tuyến giao thông kết nối từ Mũi Cà Mau ra đảo Hòn Khoai và Cảng tổng hợp lưỡng dụng Hòn Khoai."
Theo báo cáo tiến độ gần nhất tôi tìm được (tháng 6/2026), cầu kết nối (và theo đó là toàn bộ dự án phát triển trên đảo) vẫn đang được thi công tích cực, dù ở giai đoạn đầu:
Tuyến giao thông vượt biển và khu vực cảng đang thi công, ngay sau lễ khởi công 19/8/2025. Ảnh: G.B. / Thanh Niên
"...các hạng mục phụ trợ phục vụ hậu cần và thi công biển cũng đang được đẩy nhanh để đảm bảo mục tiêu hoàn thành vào cuối năm 2028. Dự án bao gồm tuyến chính dài 17,4km và tuyến nhánh dài 0,85km, kết nối trực tiếp từ khu vực Đất Mũi đến cảng Hòn Khoai."
Báo Lâm Đồng, "Cầu vượt biển Hòn Khoai tại Cà Mau: Tiến độ và quy mô công trình kỷ lục" (tháng 6/2026) · baolamdong.vn
Tầm quan trọng chiến lược
"Với độ sâu mực nước tự nhiên lớn, vùng biển Hòn Khoai có thể tiếp nhận tàu trọng tải trên 250.000 tấn mà không cần nạo vét nhiều, hiếm có ở Việt Nam."
Công Thương, "Cảng Hòn Khoai: Điểm trung chuyển trọng yếu của đồng bằng sông Cửu Long" · congthuong.vn
"Đặc biệt, cảng có hệ thống đê chắn sóng, kè bảo vệ, khu vực cập tàu quân sự, doanh trại và hạ tầng phụ trợ, đảm bảo vai trò 'hai trong một': phục vụ phát triển kinh tế và nhiệm vụ quốc phòng."
Thanh Niên, "Hòn Khoai - 'cánh cửa ngoài khơi' trên biển Tây Nam" · thanhnien.vn
"Cảng Hòn Khoai được kỳ vọng trở thành cửa ngõ giao thương quan trọng của Cà Mau nói riêng và khu vực Tây Nam Bộ nói chung."
CafeF, "Tấp nập thi công cầu đường vượt biển dài nhất Việt Nam" · cafef.vn
"Không ít chuyên gia nhìn nhận, việc triển khai đồng bộ các dự án hạ tầng trên đảo Hòn Khoai chính là sự cụ thể hóa quan điểm 'phát triển kinh tế gắn liền với bảo vệ Tổ quốc từ sớm, từ xa'."
Công ty CP Dịch vụ biển Tân Cảng (mã: TOS, tên pháp lý TCO) được nêu tên trong các bài báo về lễ khởi công là một trong ba nhà thầu thi công của dự án: không phải chủ đầu tư, và không phải nhà thầu duy nhất.
"Các nhà thầu thi công gồm Công ty TNHH Đầu tư xây dựng DACINCO; Công ty Cổ phần xây lắp Thành An 96; Công ty Cổ phần dịch vụ biển Tân Cảng (TCO). Đơn vị giám sát là Công ty Cổ phần Tư vấn xây dựng Công trình Hàng hải và Viện kỹ thuật Công trình đặc biệt."
Báo Xây Dựng · baoxaydung.vn (được xác nhận độc lập bởi SGGP, "Sẵn sàng khởi công Cảng tổng hợp lưỡng dụng Hòn Khoai")
Hội đồng quản trị TOS đã xác nhận trực tiếp vai trò này với cổ đông: đây là phát biểu có tính xác thực cao nhất hiện có, vì nó đến từ chính công ty trong một tài liệu công bố thông tin chính thức, chứ không phải qua báo chí:
"Đối với vai trò của TCO trong dự án Cảng Hòn Khoai: Dự án Cảng Hòn Khoai là dự án trọng điểm quốc gia thuộc Bộ Quốc phòng. Hiện nay, Bình đoàn 20 – Công ty TNHH MTV Tổng công ty Tân Cảng Sài Gòn và TCO tham gia dự án với vai trò thực hiện nhiệm vụ theo phân công/chỉ đạo."
Công ty CP Dịch vụ biển Tân Cảng, Biên bản họp ĐHĐCĐ thường niên 2026, mục 2.5 (nộp ngày 21/5/2026 tại Ủy ban Chứng khoán Nhà nước và Sở GDCK Hà Nội)
Cách hiểu của tôi, không phải sự thật đã nêu
Cách diễn đạt của chính công ty cố tình mập mờ: "thực hiện nhiệm vụ theo phân công/chỉ đạo" không nêu rõ TOS chịu trách nhiệm cho gói thầu, giai đoạn, hay giá trị nào. Các bài báo về lễ khởi công nêu tên DACINCO trước tiên, và trong câu tóm tắt của một tờ báo, DACINCO được nêu riêng một mình là "nhà thầu thi công." Dựa trên thứ tự đó, suy luận của tôi là TOS nhiều khả năng giữ vai trò thứ yếu hoặc được ủy quyền hơn là hợp đồng chính, dù đây là cách tôi diễn giải cách báo chí mô tả, không phải điều bất kỳ nguồn nào nói thẳng ra.
Báo cáo tài chính của chính TOS cho thấy gì
Thay vì chỉ dựa vào bình luận, tôi lấy số liệu trực tiếp từ báo cáo tài chính hợp nhất Quý II/2026 đã kiểm toán của TOS (kỳ kết thúc 30/6/2026, có số liệu so sánh tại 1/1/2026). Có hai khoản mục liên quan.
Chi phí xây dựng cơ bản dở dang (Thuyết minh V.12 trong bảng cân đối kế toán hợp nhất):
Khoản mục (VNĐ)
30/6/2026
1/1/2026
Thay đổi
Mua sắm TSCĐ
426.786.909.337
551.392.626.934
−124.605.717.597
Xây dựng cơ bản dở dang
305.092.155.708
18.764.413.956
+286.327.741.752
Sửa chữa lớn TSCĐ
2.225.666.304
2.533.154.550
−307.488.246
Tổng cộng
734.104.731.349
572.690.195.440
+161.414.535.909 (+28,2%)
Nguồn: Công ty CP Dịch vụ biển Tân Cảng, Báo cáo tài chính hợp nhất Quý II năm 2026, Thuyết minh V.12 "Chi phí xây dựng cơ bản dở dang." Mức tăng +28,2% của tổng chi phí xây dựng cơ bản dở dang gần như hoàn toàn đến từ khoản mục con "Xây dựng cơ bản dở dang," vốn tăng khoảng 16,3 lần, được bù trừ một phần bởi mức giảm ở khoản "Mua sắm TSCĐ."
Người mua trả tiền trước, riêng khoản từ Quân chủng Hải quân (Thuyết minh V.14 trong bảng cân đối kế toán hợp nhất):
Khoản mục (VNĐ)
30/6/2026
1/1/2026
Thay đổi
Trả trước ngắn hạn: Quân chủng Hải quân
950.046.868.573
614.795.575.343
+335.251.293.230 (+54,5%)
Trả trước dài hạn: Quân chủng Hải quân
414.009.317.300
434.767.672.700
−20.758.355.400 (−4,8%)
Tổng cộng khoản trả trước từ Hải quân
1.364.056.185.873
1.049.563.248.043
+314.492.937.830 (+30,0%)
Nguồn: Công ty CP Dịch vụ biển Tân Cảng, Báo cáo tài chính hợp nhất Quý II năm 2026, Thuyết minh V.14 "Người mua trả tiền trước." Quân chủng Hải quân là khách hàng có khoản trả trước lớn nhất của TOS trong cả hai kỳ nêu trên.
Giới hạn quan trọng
Cả hai thuyết minh trên đều không nêu tên "Hòn Khoai" cụ thể. Báo cáo tài chính chỉ công bố các danh mục chung ("Xây dựng cơ bản dở dang") và tên khách hàng ("Quân chủng Hải quân"), không có phân tách theo từng dự án, nên mức đóng góp doanh thu trực tiếp từ riêng Hòn Khoai không thể ước tính được từ thông tin công khai. TOS cũng đã nói rõ trong phần hỏi đáp tại ĐHĐCĐ rằng công ty không thể công bố thêm chi tiết hợp đồng do yêu cầu bảo mật và quy định từ đối tác:
"Trong thời gian tới, Công ty tiếp tục tích cực tham gia đấu thầu nhiều dự án đầu khí trong và ngoài nước. Tuy nhiên, do yêu cầu bảo mật thông tin kinh doanh và quy định của đối tác, Công ty chưa thể công bố chi tiết tại Đại hội."
Biên bản họp ĐHĐCĐ 2026 của TOS, mục 2.3 (câu trích dẫn này nói về đấu thầu dầu khí, được dẫn ở đây để cho thấy cách hành xử chung của công ty về việc không công bố chi tiết hợp đồng, không phải một phát biểu trực tiếp về Hòn Khoai)
Cách hiểu của tôi, không phải sự thật đã nêu
Tôi cho rằng việc liên hệ hai dữ kiện này (chi phí xây dựng cơ bản dở dang tăng và khoản trả trước từ Hải quân cũng tăng, trong cùng kỳ báo cáo, từ một công ty đã công khai xác nhận tham gia vào một dự án cảng do Hải quân làm chủ) là bằng chứng mạnh nhất hiện có, dù vẫn mang tính gián tiếp, cho thấy Hòn Khoai, và có thể cả hạ tầng liên quan của Hải quân như cầu kết nối, đang đóng góp vào mức tăng này. Mối quan hệ với Hải quân của TOS có thể bao gồm các hợp đồng khác mà tôi không biết, và công ty chưa công bố phân tách theo từng dự án, nên hãy xem đây là một giả thuyết cần kiểm chứng thêm, không phải một mối liên hệ nhân quả đã được xác nhận.
Bối cảnh tài chính rộng hơn (không riêng cho từng dự án)
Riêng biệt, các bình luận phân tích (không phải công bố của chính TOS) đặt Hòn Khoai trong một danh sách rộng hơn các dự án liên quan đến Hải quân/quốc phòng mà TOS được cho là hưởng lợi:
"Nhờ nằm trong hệ sinh thái của Quân chủng Hải Quân (Bộ quốc phòng) nên TOS được tham gia vào nhiều dự án hạ tầng và quốc phòng quy mô lớn như Cảng Hòn Khoai (15.000 tỷ), cầu vượt biển kết nối với đảo Hòn Khoai (25.000 tỷ), Bến số 7&8 tại cảng nước sâu Lạch Huyện (12.792 tỷ)."
Alias.vn, "TOS - Khối lượng công việc tăng cao kỷ lục" (bình luận phân tích cổ phiếu, không phải công bố của TOS) · alias.vn
Giới hạn quan trọng
Đây là bình luận phân tích của bên thứ ba, không phải tài liệu công bố của công ty hay cơ quan nhà nước. Tôi chưa thể xác minh độc lập giá trị hợp đồng hoặc phạm vi công việc cụ thể của TOS tại Hòn Khoai từ một nguồn chính thức, và cũng không tìm thấy nguồn như vậy công khai. Hãy xem các con số VNĐ gắn với từng dự án trong trích dẫn này là cách mô tả của nhà phân tích đó, không phải giá trị hợp đồng đã được TOS xác nhận. Sự tham gia của TOS cũng dường như chỉ là một trong nhiều dự án hạ tầng liên quan đến Hải quân/quốc phòng, nên riêng Hòn Khoai có thể không tách biệt được khỏi dòng doanh thu rộng hơn từ "hệ sinh thái quốc phòng" của TOS.
Cùng nguồn bình luận này còn nêu một con số tại cuối Q3/2025: khoản người mua trả tiền trước từ Quân chủng Hải quân đạt 1.916 tỷ đồng, tăng hơn 500 tỷ so với đầu năm đó. Con số này có trước các số liệu Quý II/2026 nêu trên (tổng khoản trả trước từ Hải quân là 1.364 tỷ đồng tại 30/6/2026) và, do thiếu các báo cáo quý xen giữa của TOS, hai con số không thể so sánh trực tiếp. alias.vn
Tăng trưởng và Tầm quan trọng đối với TOS: Đánh giá của tôi
Phân tích của tôi: rõ ràng là quan điểm riêng, không phải sự thật đã có nguồn
Hòn Khoai có khả năng là một yếu tố đóng góp đáng kể và đang tăng vào chi phí xây dựng cơ bản dở dang và khoản trả trước của khách hàng tại TOS, nhưng thông tin công khai hiện có không cho phép tôi (hay bất kỳ nhà phân tích bên ngoài nào mà tôi biết) nêu ra một con số doanh thu hoặc lợi nhuận đã được xác nhận cho riêng dự án này. Bất kỳ ai sử dụng mối liên hệ này cho mục đích đầu tư nên xem đây là một giả thuyết cần kiểm chứng thêm (ví dụ, thông qua liên hệ trực tiếp với công ty hoặc các báo cáo quý sau này), không phải một sự thật đã được xác định.
⚓